Pricing COVID risks into contracts a major challenge: CI panel

Don Wall
Pricing COVID risks into contracts a major challenge: CI panel

The newest COVID-related challenge buffeting 新澳门六合彩开奖结果2023鈥檚 construction sector is not keeping workers safe or creating vaccine policies but rather it鈥檚 properly pricing risks in a world of inflated costs and unpredictable supply chains.

The Canadian Institute (CI) assembled three legal and claims experts Feb. 24 for a panel titled Managing Your Projects, COVID-Related Risks and Delays.

Andre Brace, senior director of construction solutions for FTI Consulting, Sahil Shoor, partner with Gowling WLG, and Robert Poole, senior managing director with FTI, highlighted best practices in an online session moderated by conference co-host Howard Krupat, partner with DLA Piper.

鈥淭o me, the biggest challenge now related to COVID in particular is really relating to claims, contracts and pricing of work. I think those are real challenges that organizations on both the owner and the contractor side are going to face,鈥 Poole stated, noting numerous complex COVID disputes in the sector as owners and contractors wade through delay and productivity issues.

鈥淒isentangling all of that is going to be a major challenge. So my view is, the challenges going forward are more related to the practical side, the claims side, and less on the actual impacts of COVID.鈥

As claims pile up, the panellists said, it is more essential than ever to ensure high-quality record-keeping. Concerted efforts must be made to ensure there are corporate resources available to undertake those record-keeping and disentanglement efforts.

The resources needed to prepare the claims 鈥渄on鈥檛 come out of thin air,鈥 Poole said. 鈥淚t needs a lot of work to prepare and analyze claims or to consider them whether or not they are actually substantiating the claims that are made鈥nd at the same time you鈥檝e got your regular business you鈥檙e supposed to be doing.鈥

The hiring of claims experts need not increase the adversarial nature of dealing with a COVID-related dispute, Poole said.

Their forensic approach is effective in demonstrating true COVID-related causes and effects, and attempts to reconcile losses. Methods used include delay analysis and loss-of-productivity analysis including industry studies and project benchmarking.

鈥淢y suggestion is, very often it鈥檚 in the interests of clients on both the owner and the contractor side to really appoint legal and claims experts who know how these claims should be prepared and substantiated,鈥 said Poole.

鈥淭hen the second thing is, I鈥檝e got a really strong opinion about working collaboratively.鈥

Krupat noted there has been a willingness to collaborate on disputes.

鈥淓specially about a year into the pandemic, there was a strong willingness on the part of both owners and contractors to negotiate their way through these claims rather than to resort to a formal dispute-resolution process,鈥 he said. 鈥淚鈥檝e seen some very positive results through mediations.鈥

The better the records, Brace said, the better the analysis that can be done.

鈥淥ne of the things that I have found, particularly having spent a lot of my career working in projects, is that we know where to look in many cases, especially with COVID claims that can be very complex, and we鈥檒l have to push the boundaries of typically where we find the information.鈥

Onsite personnel issues adding to costs are well understood by now and include absenteeism, refusal to work and mental health impacts, Brace said.

鈥淓ven if they鈥檙e working at 100-per-cent productivity or the planned productivity levels, if you鈥檝e got half the people, you鈥檙e not going to achieve the schedule and the overall project completion that you鈥檙e expecting,鈥 said Brace.

鈥淎t the start of the shift, before even starting to do productive work, we鈥檙e doing these new activities that are separate and distinct from the actual time loss or productivity loss that鈥檚 happening.鈥

Supply chain issues can have many causes and now there are political protests at borders, Poole noted.

鈥淭here鈥檚 tons of potential for things to go wrong. It鈥檚 quite amazing that more things do not go wrong,鈥 he said. 鈥淲e鈥檝e seen these closing borders, restrictions on movements of goods or whether it鈥檚 just supply chain, or manufacturing plants having a problem with labour.鈥

It all adds up to a greater onus on estimators and drafters of contracts to strive for improved contracts that more carefully incorporate all possible risks, Shoor said.

鈥淲hat you should be doing, the first step in my respectful view, is you should be looking at the contract in question as to what steps you can and cannot take to mitigate the risk and damage in advance of that event actually taking place,鈥 he said, noting that 鈥渇oreseeability鈥 is an increasingly important concept.

鈥淏e proactive in terms of how better you can have the ability to meet the contract obligations, thinking about it routinely and planning it accordingly.鈥

 

Follow the author on Twitter .